× Didn't find what you were looking for? Ask a question
Top Posters
Since Sunday
r
4
L
4
3
d
3
M
3
l
3
V
3
s
3
d
3
a
3
g
3
j
3
New Topic  
thegingercoffee thegingercoffee
wrote...
Posts: 660
Rep: 0 0
6 years ago
The critical path of a project
 a. cannot change once the project has started.
  b. is the longest path in the overall network diagram.
  c. always has a negative slack.
  d. always has a positive slack.
Read 41 times
1 Reply
Replies
Answer verified by a subject expert
alohacharlesalohacharles
wrote...
Top Poster
Posts: 910
Rep: 4 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

wrote...

6 years ago
this is exactly what I needed
wrote...

Yesterday
Thanks
wrote...

2 hours ago
You make an excellent tutor!
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1686 People Browsing
Related Images
  
 548
  
 227
  
 1115