The critical path of a project
 a. cannot change once the project has started.
  b. is the longest path in the overall network diagram.
  c. always has a negative slack.
  d. always has a positive slack.
Read 39 times
1 Reply
Replies
Answer verified by a subject expert
alohacharlesalohacharles
wrote...
Top Poster
Posts: 910
Rep: 4 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

wrote...

6 years ago
Good timing, thanks!
wrote...

Yesterday
Brilliant
wrote...

2 hours ago
I appreciate what you did here, answered it right Smiling Face with Open Mouth
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1033 People Browsing
Related Images
  
 539
  
 215
  
 631
Your Opinion