Calculate the latest finish for Task D if one of its successors, Task F, has a latest start on day 9, its other successor, Task E, has a latest start on day 10, and the duration of Task D is 2 days.
 a. day 9
  b. day 10
  c. day 12
  d. Cannot be calculated based upon information given.
Read 80 times
2 Replies
Replies
Answer verified by a subject expert
CologicoonCologicoon
wrote...
Top Poster
Posts: 949
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

wrote...
4 years ago
Thankyou!
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  941 People Browsing
Related Images
  
 112
  
 191
  
 183
Your Opinion
Who will win the 2024 president election?
Votes: 119
Closes: November 4