Hummer Hummer
wrote...
Posts: 716
Rep: 0 0
6 years ago
A project requires at least 28 worker-days to complete the project. What is the shortest time estimate for completion if the project is constrained to two workers per day? Assume no task requires more than one worker and the tasks can be completed independent of each other.
 a. 56 days
  b. 28 days
  c. 14 days
  d. Additional information is needed to determine the project duration.
Read 202 times
3 Replies
Replies
Answer verified by a subject expert
babyfacelovebabyfacelove
wrote...
Top Poster
Posts: 903
Rep: 8 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

wrote...
3 years ago
thank you
wrote...
3 years ago
great!
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  956 People Browsing
Related Images
  
 2489
  
 349
  
 649
Your Opinion
Do you believe in global warming?
Votes: 419