Assume that activity G has the following times: Early start time = 7 days Early finish time = 13 days Late start time = 15 days Late finish time = 21 days Which of the following statements is TRUE about activity G?
A) Activity G has a slack time of 8 days.
B) Activity G takes 2 days to complete.
C) Activity G takes 14 days to complete.
D) Activity G is on the critical path.
Textbook 
Operations Management: Processes and Supply Chains

Operations Management: Processes and Supply Chains


Edition: 11th
Authors:
Read 272 times
2 Replies
Replies
Answer verified by a subject expert
pennocpennoc
wrote...
Posts: 396
Rep: 4 0
7 years ago
Sign in or Sign up in seconds to unlock everything for free
More solutions for this book are available here
1

Related Topics

silverbullet Author
wrote...
7 years ago
needed this today

thanks so much
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1154 People Browsing
Related Images
  
 1558
  
 557
  
 295