Following are the three time estimates for a task in a project:

optimistic completion time = 2 weeks
most likely completion time = 4 weeks
pessimistic completion time = 7 weeks

Compute the expected time for the task.
A) 3.5 weeks
B) 4.167 weeks
C) 5.23 weeks
D) 5.75 weeks
Textbook 
Managing Supply Chain and Operations: An Integrative Approach

Managing Supply Chain and Operations: An Integrative Approach


Edition: 1st
Authors:
Read 90 times
2 Replies
Replies
Answer verified by a subject expert
delite_40delite_40
wrote...
Posts: 389
Rep: 7 1
6 years ago
Sign in or Sign up in seconds to unlock everything for free
More solutions for this book are available here
1

Related Topics

mcv4u Author
wrote...
6 years ago
Thank you
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  801 People Browsing
Related Images
  
 160
  
 222
  
 2704
Your Opinion
Which industry do you think artificial intelligence (AI) will impact the most?
Votes: 379