Activity R on a CPM network has predecessors M and N, and has successor S. R has duration 5. N's late finish is 18, while M's is 20. S's late start is 14. Which of the following is definitely true?
A) R has no slack but is not critical.
B) S is a critical activity.
C) The set of times cannot all be possible.
D) R is critical and has zero slack.
E) N is a critical activity.
Textbook 
Operations Management

Operations Management


Edition: 10th
Authors:
Read 64 times
1 Reply
Replies
Answer verified by a subject expert
HplyEvrAftrHplyEvrAftr
wrote...
Top Poster
Posts: 1033
7 years ago
Sign in or Sign up in seconds to unlock everything for free
More solutions for this book are available here
1

Related Topics

retownes Author
wrote...

7 years ago
I appreciate what you did here, answered it right Smiling Face with Open Mouth
wrote...

Yesterday
this is exactly what I needed
wrote...

2 hours ago
Thanks
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  995 People Browsing
Related Images
  
 362
  
 389
  
 1276
Your Opinion
Do you believe in global warming?
Votes: 488