Top Posters
Since Sunday
w
5
a
3
j
2
a
2
t
2
u
2
r
2
j
2
j
2
l
2
d
2
y
2
New Topic  
sinnefoula sinnefoula
wrote...
Posts: 1533
Rep: 1 0
7 years ago
Three critical path activities are candidates for crashing on a CPM network. Activity details are in the table below.

Activity   Normal Time   Normal Cost   Crash Duration   Crash Cost
X   8 days   $6,000   6 days   $8,000
Y   3 days   $1,800   2 days   $2,400
Z   12 days   $5,000   9 days   $7,700

a. What is the crash cost per unit time for each of the three activities?
b. Which activity should be crashed first to cut one day from the project's duration; how much is added to project cost?
c. Which activity should be the next activity crashed to cut a second day from the project's duration; how much is added to project cost?
Textbook 
Operations Management

Operations Management


Edition: 10th
Authors:
Read 79 times
2 Replies
Replies
Answer verified by a subject expert
HplyEvrAftrHplyEvrAftr
wrote...
Top Poster
Posts: 1033
7 years ago
Sign in or Sign up in seconds to unlock everything for free
More solutions for this book are available here
1

Related Topics

sinnefoula Author
wrote...
7 years ago
Correct again, thank you
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1199 People Browsing
 226 Signed Up Today
Related Images
  
 295
  
 361
  
 647
Your Opinion
What's your favorite math subject?
Votes: 559