A critical path refers to:
A) a sequence of task activities whose order and durations indirectly affect the completion date of a project.
B) a sequence of task activities whose order must be performed in parallel.
C) a sequence of task activities whose duration cannot last more than 40 percent of the time allotted to the project.
D) a sequence of task activities whose order and durations directly affect the completion date of a project.
E) none of the above.
Textbook 
Essentials of Systems Analysis and Design

Essentials of Systems Analysis and Design


Edition: 6th
Authors:
Read 74 times
2 Replies
Replies
Answer verified by a subject expert
pisdoktorpisdoktor
wrote...
Posts: 418
Rep: 3 0
7 years ago
Sign in or Sign up in seconds to unlock everything for free
More solutions for this book are available here
1

Related Topics

almostutterly Author
wrote...
6 years ago
Ty soo very much
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  600 People Browsing
Related Images
  
 610
  
 1128
  
 755
Your Opinion

Previous poll results: What's your favorite math subject?