Casey Construction abandoned its $23 million North County road project after spending $7 million. By this time, one progress payment of $5 million had been made. The county immediately contracted with Beachwood Corp. to take over and finish the project for $21 million. Expectation damages for Casey Construction would be
a. the difference between $16 and $21 million.
b. the difference between $21 and $23 million.
c. zero, since Casey did $2 million of work where no payment was received.
d. none; only consequential damages might apply.
e. the difference between $18 and $21 million.
Textbook 
The Law and Business Administration in Canada

The Law and Business Administration in Canada


Edition: 14th
Authors:
Read 100 times
2 Replies
Replies
Answer verified by a subject expert
MiY4GiMiY4Gi
wrote...
Top Poster
Posts: 676
7 years ago
Sign in or Sign up in seconds to unlock everything for free
More solutions for this book are available here
1

Related Topics

ohiosr Author
wrote...
6 years ago
Thanks for helping
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1292 People Browsing
Related Images
  
 1082
  
 663
  
 982
Your Opinion