Transcript
August 20th, 2016
Reduction of Rework Parts for Pin
Customers
Material Suppliers
Hardware Suppliers
Employee Agencies
Engineering Drawings
Customer Standards
Customer Specification
Purchase Orders
Parts Conformance
Parts Non-Conformance
MRB Report
COFC
Rework SOPs
Vendor Performance Index
Customers
Vendors
LHM
Finishing Machine Work
Toll Gate Inspection
& Processing
Final Inspection at LHM
Rough Machine Work
Withdraw Material
DEFINE
LHM SIPOC DIAGRAM
DEFINE
MEASURE
Data Collection
{5C22544A-7EE6-4342-B048-85BDC9FD1C3A}Part Number
Name
Aircraft
QTY/YR
$/PC
Processing $/PC
Process Sequence
Min. Batch QTY
Batches/YR
Weight [lbs]
161Axxxx-1
Pin
737-X
1500
400
150
NI/MPI/SP/CR/GR/CAD/MPI/PR/P
80
18
1.97
Shipping Cost: $0.25/lb
Workforce Cost: $75/hr
Average part rework/ batch: 4
Average data from 2010 -2015
Average 5% defective
Minimize part
non-conformances
after parts are in their
finished state
Fishbone Diagram – Causes & Effects of Low Customer Satisfaction
Surface Coating
Personnel not trained properly
Method
Procedure for Packaging not Updated
Visual Inspection not required before delivery
Manpower
Machine
Operator did not follow procedure
External presence (Vendor) damaged parts
Poor Material
Material
Environment
Measurement
Too many staffs in the production area
Operator did not follow procedure
Sensor Malfunction
Broken Equipment
Broken Equipment
Parts moved, arranged incorrectly
Additional Activities
ANALYZE
IMPROVE
CONTROL
Proposed Solutions
Initiate use of designated part packages
PO’s to be certified by vendor with critical product dimensions before sending it back to LHM
Reduce non-conformances by regular audits of the vendor’s progress by LHM’s Quality Manager
Shipment of an extra set of calibrated gauges to be sent to the vendor
Minimized source of defects for smaller parts
Help transition into dealing with larger part orders in the future
The team will be able to additionally identify at least 30 % of the non-conformances saving LHM approximately $50, 000 per year.
Project Outcome
Questions
|
|