Which of the following statements concerning work packages is NOT correct?
 a. Work packages are the basis for subsequent project planning activities.
  b. Work packages are the basis for subsequent project control activities.
  c. Work packages are activity elements with detailed descriptions of tasks and dependencies
  d. Work packages are the elements at the lowest level of the WBS.
Read 119 times
1 Reply
Replies
Answer verified by a subject expert
abenhadabenhad
wrote...
Top Poster
Posts: 859
Rep: 3 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

riz Author
wrote...

6 years ago
This site is awesome
wrote...

Yesterday
Just got PERFECT on my quiz
wrote...

2 hours ago
You make an excellent tutor!
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  717 People Browsing
 117 Signed Up Today
Related Images
  
 299
  
 1270
  
 286
Your Opinion