Using Table 7.5, every day the construction crew is on-site costs 1000. What activities would you consider crashing to reduce the project completion cost?
 
  A) Activity E
  B) Activity F
  C) Activity G
  D) All of these activities would be candidates for crashing.
Read 51 times
1 Reply

Related Topics

Replies
wrote...
6 years ago
C