mjhgfd mjhgfd
wrote...
6 years ago
It costs 75 per day for each day that a construction crew is on site. The project manager determines that most activities can be crashed and has listed the crashing costs next to the minimum time for each activity.
 
  Use this information to determine the lowest cost for this project. All times given are in days.
 
  Activity Normal Time Minimum Time Crash Cost (/day) Predecessor
  A 10 6 70 --
  B 6 3 40 --
  C 2 2 -- B
  D 4 2 60 C
  E 6 4 80 A
  F 8 5 90 D, E
  A) 1,720
  B) 1,750
  C) 1,780
  D) 1,810
Read 43 times
2 Replies

Related Topics

Replies
wrote...
6 years ago
C
mjhgfd Author
wrote...
6 years ago
I hope they're paying you for this lol
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1337 People Browsing
Related Images
  
 249
  
 634
  
 301
Your Opinion
Which 'study break' activity do you find most distracting?
Votes: 741

Previous poll results: Who's your favorite biologist?