Use the project described in the table to determine the total resources required for this project during week 1 if a worker is expected to devote half-time (four hours per day) to this project.
 
  Assume that the project work is conducted on a 5-day-per-week basis.
 
  Activity Duration Predecessor
  A 5 days --
  B 4 days A
  C 5 days A
  D 6 days B
  E 6 days C, D
  F 6 days E
  A) 40 hours
  B) 20 hours
  C) 28 hours
  D) 36 hours
Read 49 times
2 Replies
Replies
Answer verified by a subject expert
Jumana00Jumana00
wrote...
Top Poster
Posts: 918
Rep: 7 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

chotard1 Author
wrote...
6 years ago
THX *so* much
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  887 People Browsing
Related Images
  
 120
  
 216
  
 940
Your Opinion
Which of the following is the best resource to supplement your studies:
Votes: 300