Use the project described in the table to determine the total resources required for this project during week 1 if a worker is expected to devote half-time (four hours per day) to this project. Assume that the project work is conducted on a 5-day-per-week basis.

Activity   Duration   Predecessor
A   5 days   --
B   4 days   A
C   5 days   A
D   6 days   B
E   6 days   C, D
F   6 days   E

A) 40 hours
B) 36 hours
C) 20 hours
D) 28 hours
Textbook 
Project Management: Achieving Competitive Advantage

Project Management: Achieving Competitive Advantage


Edition: 4th
Author:
Read 214 times
3 Replies
Yuppp
Replies
Answer verified by a subject expert
flammableflammable
wrote...
Top Poster
Posts: 1729
8 years ago
Sign in or Sign up in seconds to unlock everything for free
More solutions for this book are available here
1

Related Topics

Louie928 Author
wrote...
8 years ago
Exam is today, I appreciate your help so much
Yuppp
wrote...
8 years ago
Thanks for the update! Happy Holidays
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1032 People Browsing
Related Images
  
 675
  
 333
  
 613
Your Opinion
Which industry do you think artificial intelligence (AI) will impact the most?
Votes: 405