If an activity can be completed in 10 weeks at a cost of 3,200 instead of the normal time of 12 weeks at a cost of 2,400, then the crash cost per week for the given activity is _____.
 A) 200
  B) 400
  C) 600
  D) 800
Read 42 times
1 Reply
Replies
Answer verified by a subject expert
Jumana00Jumana00
wrote...
Top Poster
Posts: 918
Rep: 7 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

Heskeksndfb Author
wrote...

6 years ago
Good timing, thanks!
wrote...

Yesterday
I appreciate what you did here, answered it right Smiling Face with Open Mouth
wrote...

2 hours ago
Smart ... Thanks!
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1216 People Browsing
Related Images
  
 285
  
 872
  
 353
Your Opinion
Which 'study break' activity do you find most distracting?
Votes: 820