The earliest finish time for an activity
 a. is calculated by adding the activity's estimated duration to its earliest start time.
  b. is the same as the earliest start time of the activity's predecessor.
  c. should not be delayed or would cause the project to be delayed.
  d. is dependent upon the start time of its successor activities.
Read 36 times
1 Reply
Replies
Answer verified by a subject expert
lightingmcqueenlightingmcqueen
wrote...
Top Poster
Posts: 911
Rep: 3 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

Micky5490! Author
wrote...

6 years ago
Helped a lot
wrote...

Yesterday
Smart ... Thanks!
wrote...

2 hours ago
Brilliant
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1159 People Browsing
Related Images
  
 173
  
 455
  
 2134
Your Opinion
Which industry do you think artificial intelligence (AI) will impact the most?
Votes: 405