The earliest finish time for an activity
 a. is calculated by adding the activity's estimated duration to its earliest start time.
  b. is the same as the earliest start time of the activity's predecessor.
  c. should not be delayed or would cause the project to be delayed.
  d. is dependent upon the start time of its successor activities.
Read 44 times
1 Reply
Replies
Answer verified by a subject expert
lightingmcqueenlightingmcqueen
wrote...
Top Poster
Posts: 911
Rep: 3 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

Micky5490! Author
wrote...

6 years ago
This site is awesome
wrote...

Yesterday
Brilliant
wrote...

2 hours ago
Thank you, thank you, thank you!
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1084 People Browsing
Related Images
  
 228
  
 369
  
 268
Your Opinion
Which is the best fuel for late night cramming?
Votes: 146

Previous poll results: Do you believe in global warming?