A project has the precedence requirements and activity durations shown in the table. After he draws the network, the project manager decides that activities H and I can be represented by a hammock activity.
 
  What are the early start and late finish times associated with this hammock activity?
 
   Time Predecessor
  A 7
  B 8 A
  C 13 B
  D 8 C
  E 7 A
  F 6 E
  G 6 A
  H 11 G
  I 12 H
  J 14 D, F, I
  A) 13, 36
  B) 13, 24
  C) 24, 36
  D) 7, 36
Read 45 times
2 Replies

Related Topics

Replies
wrote...
6 years ago
A
Inspectum Author
wrote...
6 years ago
This helps so much, thank you for responding so quickly...