A project has the precedence requirements and activity durations shown in the table. After he draws the network, the project manager decides that activities E and F can be represented by a hammock activity.
 
  What are the duration and the early start time associated with this hammock activity?
 
   Time Predecessor
  A 7
  B 8 A
  C 13 B
  D 8 C
  E 7 A
  F 6 E
  G 6 A
  H 11 G
  I 12 H
  J 14 D, F, I
  A) 13, 36
  B) 7, 0
  C) 13, 7
  D) 7, 14
Read 64 times
1 Reply

Related Topics

Replies
wrote...
6 years ago
C
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1055 People Browsing
Related Images
  
 279
  
 6193
  
 140
Your Opinion
What's your favorite math subject?
Votes: 314