Activity R on a CPM network has predecessors M and N, and has successor S. R has duration 5. N's late finish is 18, while M's is 20. S's late start is 14. Which of the following is definitely true?
 
  A) R is critical and has zero slack.
  B) R has no slack but is not critical.
  C) The set of times cannot all be possible.
  D) N is a critical activity.
  E) S is a critical activity.
Read 48 times
1 Reply
Replies
Answer verified by a subject expert
leannaolsenleannaolsen
wrote...
Top Poster
Posts: 875
Rep: 3 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

jaycezhao Author
wrote...

6 years ago
Brilliant
wrote...

Yesterday
Thanks for your help!!
wrote...

2 hours ago
This site is awesome
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1141 People Browsing
Related Images
  
 1103
  
 259
  
 578