MRP is a computer-driven information system that translates end-item demand into raw materials, component parts, and subassemblies requirements. It works backward from the due date using _________, and other production information's. Which of the following information does not fit in the previous sentence?
 a. lead times c. bills of materials (BOM)
  b. item cost d. lot sizes
Read 147 times
3 Replies
Replies
Answer verified by a subject expert
lamaituyalamaituya
wrote...
Top Poster
Posts: 887
Rep: 8 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

jay123 Author
wrote...
6 years ago
I know this sounds cliche, but I was thinking the same thing. Thanks for confirming
wrote...
3 years ago
Thank you
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  923 People Browsing
Related Images
  
 1166
  
 86
  
 257
Your Opinion
Who's your favorite biologist?
Votes: 587