If the project needs accelerated, efforts should be concentrated on
 a. every activity with long estimated durations.
  b. activities on the critical path with short durations to make them shorter.
  c. those activities on the path that are near-term or have long estimated durations.
  d. all the near term activities in the project.
Read 59 times
1 Reply
Replies
Answer verified by a subject expert
jgfndjgfnd
wrote...
Top Poster
Posts: 871
Rep: 1 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

fuat Author
wrote...

6 years ago
Smart ... Thanks!
wrote...

Yesterday
I appreciate what you did here, answered it right Smiling Face with Open Mouth
wrote...

2 hours ago
this is exactly what I needed
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  547 People Browsing
Related Images
  
 217
  
 478
  
 599
Your Opinion

Previous poll results: Do you believe in global warming?