A contractor bidding on a fixed-price project must develop
 a. accurate and complete cost estimates and include sufficient contingency costs.
  b. a well-defined project with low risk.
  c. techniques to control costs and reduce expenses to make a larger profit.
  d. techniques to determine the cost-at-completion with actual expenditures.
Read 64 times
1 Reply

Related Topics

Replies
wrote...
6 years ago
a