A key for developing project cost estimates is to:
 
  A) Cost the project while considering the total package.
  B) Cost the project on a work package and task basis.
  C) Cost the project on a major module basis.
  D) Cost the project and add 33 for contingency.
Read 96 times
2 Replies
Replies
Answer verified by a subject expert
Beka128Beka128
wrote...
Top Poster
Posts: 919
Rep: 4 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

wrote...
3 years ago
..
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  998 People Browsing
Related Images
  
 301
  
 448
  
 132
Your Opinion
How often do you eat-out per week?
Votes: 81

Previous poll results: What's your favorite coffee beverage?