× Didn't find what you were looking for? Ask a question
Top Posters
Since Sunday
a
5
k
5
c
5
B
5
l
5
C
4
s
4
a
4
t
4
i
4
r
4
r
4
New Topic  
Hummer Hummer
wrote...
Posts: 716
Rep: 0 0
6 years ago
Your most recent project performance report indicates that your cumulative Schedule Performance Index (SPI) is .85 and your cumulative Cost Performance Index (CPI) is .90 . What conclusions can you draw from these performance indices? What actions might you take to address project performance based on these results?
Read 386 times
1 Reply

Related Topics

Replies
wrote...
6 years ago
Key concepts to be covered in the response could include, but are not limited to:

The schedule performance index (SPI) is a measure of schedule efficiency expressed as the ration of EV to PV. The SPI of .85 demonstrates that our project is proceeding less efficiently than planned and is behind schedule.

The cost performance index (CPI) is a measure of cost efficiency of budgeted resources, expressed as the ratio of EV to AC. The CPI of .90 demonstrates that our project is over budget, and that we are only receiving 0.90 worth of results for every dollar we have spent.

Given this information, we can also calculate the Estimate to Complete (ETC) and the Estimate at Completion (EAC), which are the expected cost needed to finish all the remaining project work, and the expected cost of completing all work.
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  931 People Browsing
Related Images
  
 244
  
 1117
  
 276
Your Opinion
What's your favorite coffee beverage?
Votes: 274