Using Table 7.14, if the expected time for activity C is changed to 12 weeks, by how many weeks will the project's expected completion time increase?
 
  A) It will not change.
  B) It will increase by one week.
  C) It will increase by two weeks.
  D) It will increase by three weeks.
Read 51 times
1 Reply
Replies
Answer verified by a subject expert
thundercats33thundercats33
wrote...
Top Poster
Posts: 918
Rep: 5 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

tony911t Author
wrote...

6 years ago
Brilliant
wrote...

Yesterday
This helped my grade so much Perfect
wrote...

2 hours ago
Smart ... Thanks!
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  555 People Browsing
Related Images
  
 313
  
 443
  
 712