kekule kekule
wrote...
Posts: 687
Rep: 0 0
6 years ago
Create a minimum cost chase plan for the forecast shown in the table. There is no beginning inventory and regular production capacity is 350 units.
 
  Overtime costs 20 extra and is limited to 50 units per month and subcontracting is limited to 100 units per month and costs 15 per unit. Back orders cost 40 per unit and there is a cost of 5 per month to hold a unit in inventory. There is room for only 100 units in inventory. What is the total plan cost?
 
  Month Forecast Regular Overtime Subcontracting Ending Inventory
  January 250
  February 400
  March 500
  April 350
  What will be an ideal response?
Read 69 times
1 Reply
Replies
Answer verified by a subject expert
taniaaaaaataniaaaaaa
wrote...
Top Poster
Posts: 946
Rep: 5 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

kekule Author
wrote...

6 years ago
Brilliant
wrote...

Yesterday
Just got PERFECT on my quiz
wrote...

2 hours ago
Thanks
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  842 People Browsing
Related Images
  
 279
  
 166
  
 575
Your Opinion
What's your favorite math subject?
Votes: 315

Previous poll results: How often do you eat-out per week?