What is the minimum cost completion time for this project if the activities have normal and crash costs as indicated and there is a 1,000 fixed cost for each day on site plus a 500 penalty for each activity that is crashed? The crash costs
 
  represent the cost of a fully expedited activity. For example, reducing activity Y from 13 days to 12 days costs an extra 100 on top of the 500 expediting cost for a total cost of 2,600. Reducing Y from 13 days to 10 days costs an extra 300 on top of the 500 expediting cost, for a total activity cost of 2,800.
 
  Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost
  Z 2 2,000 2 2,000
  Y 13 2,000 10 2,300
  X 19 2,000 15 3,000
  W Z 18 2,000 15 3,000
  V X 10 2,000 9 3,000
  U Y 13 2,000 11 3,000
  T W 18 2,000 14 4,000
  S V 4 2,000 3 3,000
  R U 6 2,000 5 3,000
  Q R, S 15 2,000 13 3,000
  P T 13 2,000 12 3,000
  N P, Q 4 2,000 4 2,000
Read 48 times
1 Reply
Replies
Answer verified by a subject expert
schoolboy4367schoolboy4367
wrote...
Top Poster
Posts: 1181
6 years ago
Sign in or Sign up in seconds to unlock everything for free
This verified answer contains over 130 words.
1

Related Topics

banoshaher Author
wrote...

6 years ago
Helped a lot
wrote...

Yesterday
this is exactly what I needed
wrote...

2 hours ago
This helped my grade so much Perfect
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1265 People Browsing
Related Images
  
 4132
  
 83
  
 1974
Your Opinion
Where do you get your textbooks?
Votes: 372