lexisastudent lexisastudent
wrote...
Posts: 619
Rep: 0 0
6 years ago
A project consists of eleven activities (all times are given in days) and has worker requirements as indicated in the table. Assume that all six workers employed by this organization are generalists and are able to work on any of the tasks.
 
  What is the fastest the project can be completed?
 
  Activity Activity time Workers Needed Predecessor
  A 10 1
  B 4 2
  C 7 3 A
  D 4 1 A
  E 8 2 B
  F 9 3 C,E
  G 13 1 D
  H 14 2 E,G
  J 13 3 F
  K 10 1 H, J
  L 5 2 K
  A) 54 days
  B) 56 days
  C) 58 days
  D) 60 days
Read 105 times
1 Reply
Replies
Answer verified by a subject expert
ashxeveashxeve
wrote...
Top Poster
Posts: 917
Rep: 1 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

lexisastudent Author
wrote...

6 years ago
This site is awesome
wrote...

Yesterday
Thanks
wrote...

2 hours ago
Brilliant
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1118 People Browsing
Related Images
  
 505
  
 833
  
 662
Your Opinion
Where do you get your textbooks?
Votes: 447