A project consists of eleven activities (all times are given in days) and has worker requirements as indicated in the table. Assume that all four workers employed by this organization are generalists.
 
  What schedule is attainable if the number of workers is not an issue? What is the fastest the project can be completed while constrained by the four worker limitation?
 
  Activity Activity time Workers Needed Predecessor
  A 10 1
  B 4 2
  C 7 3 A
  D 4 1 A
  E 8 2 B
  F 9 3 C,E
  G 13 1 D
  H 14 2 E,G
  J 13 3 F
  K 10 1 H, J
  L 5 2 K
Read 123 times
1 Reply
Replies
Answer verified by a subject expert
npalmierinpalmieri
wrote...
Top Poster
Posts: 886
Rep: 4 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
This verified answer contains over 180 words.
1

Related Topics

arock1 Author
wrote...

6 years ago
Smart ... Thanks!
wrote...

Yesterday
Thanks for your help!!
wrote...

2 hours ago
This site is awesome
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  415 People Browsing
 136 Signed Up Today
Related Images
  
 227
  
 359
  
 164
Your Opinion
Which country would you like to visit for its food?
Votes: 264