The order of magnitude cost estimate is used when:
 
  A) Ballpark estimates are not considered accurate enough.
  B) Historical data are readily available.
  C) Information or time is scarce.
  D) Parametric estimation has already been performed.
Read 79 times
2 Replies

Related Topics

Replies
wrote...
6 years ago
C
wrote...
6 years ago
Thank you for answering