A systems analyst is paid at the rate of 50/hour and will be needed for 40 hours. Her employer uses an overhead multiplier of 60 and does not factor in personal time. Her total direct labor cost should be billed at:
 
  A) 2,000.
  B) 3,200.
  C) 1,250.
  D) 4,500.
Read 74 times
2 Replies

Related Topics

Replies
wrote...
6 years ago
B