A project team assesses their primary risk factor's probability of failure with a maturity risk of 0.3, a complexity risk of 0.7, and a dependency risk of 0.8. The probability of failure is:
 
  A) Less than or equal to 0.3.
  B) Greater than 0.3 but less than or equal to 0.55.
  C) Greater than 0.56 but less than or equal to 0.89.
  D) Greater than or equal to 0.9.
Read 55 times
1 Reply

Related Topics

Replies
wrote...
6 years ago
C
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  929 People Browsing
Related Images
  
 285
  
 1376
  
 595
Your Opinion
Which country would you like to visit for its food?
Votes: 214

Previous poll results: Do you believe in global warming?