A writer estimates it will take three months to generate spiffy documents to accompany a seminal work in operations management. He grossly underestimates the time required and misses his deadline by two months. This estimate was:
 
  A) Objective and accurate.
  B) Subjective and accurate.
  C) Objective and inaccurate.
  D) Subjective and inaccurate.
Read 68 times
1 Reply

Related Topics

Replies
wrote...
6 years ago
D