Clancy's Motors has the following demand to meet for custom manufactured fuel injector parts. The holding cost for that item is .75 per month and each setup costs 150. Lead time is 0 months.
 
  Calculate the planned order releases using: (a) the EOQ technique, and (b) the POQ technique.
  What are the costs of each plan, including the holding cost of any inventory left over after month 7?
 
  Month 1 2 3 4 5 6 7
  Requirement 100 150 200 150 100 150 250
Read 48 times
1 Reply
Replies
Answer verified by a subject expert
cvallierecvalliere
wrote...
Top Poster
Posts: 940
Rep: 4 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

chem1111 Author
wrote...

6 years ago
Smart ... Thanks!
wrote...

Yesterday
Helped a lot
wrote...

2 hours ago
Good timing, thanks!
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1282 People Browsing
Related Images
  
 296
  
 282
  
 360
Your Opinion
Which is the best fuel for late night cramming?
Votes: 234