Micky5490! Micky5490!
wrote...
Posts: 660
Rep: 0 0
6 years ago
Analysis of a PERT problem shows the estimated time for the critical path to be 108 days with a variance of 64. There is a .90 probability that the project will be completed before approximately day:
 
  A) 98.
  B) 108.
  C) 109.
  D) 115.
  E) 118.
Read 46 times
1 Reply
Replies
Answer verified by a subject expert
kallierfkallierf
wrote...
Top Poster
Posts: 906
Rep: 6 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

Micky5490! Author
wrote...

6 years ago
I appreciate what you did here, answered it right Smiling Face with Open Mouth
wrote...

Yesterday
this is exactly what I needed
wrote...

2 hours ago
This helped my grade so much Perfect
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  995 People Browsing
Related Images
  
 246
  
 29
  
 58
Your Opinion
Who's your favorite biologist?
Votes: 586

Previous poll results: How often do you eat-out per week?