A PERT project has 45 activities, 19 of which are on the critical path. The estimated time for the critical path is 120 days. The sum of all activity variances is 64, while the sum of variances along the critical path is 36.
 
  What is the probability that the project can be completed between days 108 and 120?
  A) -2.00
  B) 0.0227
  C) 0.1058
  D) 0.4773
  E) 0.9773
Read 35 times
1 Reply
Introduction to Operations and Supply Chain Management, 4e (Bozarth/Handfield)
Replies
Answer verified by a subject expert
monmon
wrote...
Top Poster
Posts: 914
Rep: 8 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

bsktball509 Author
wrote...

6 years ago
This helped my grade so much Perfect
wrote...

Yesterday
Thanks for your help!!
wrote...

2 hours ago
Thanks
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1294 People Browsing
Related Images
  
 43
  
 520
  
 254
Your Opinion
Which industry do you think artificial intelligence (AI) will impact the most?
Votes: 352

Previous poll results: What's your favorite math subject?