A PERT project has 45 activities, 19 of which are on the critical path. The estimated time for the critical path is 120 days. The sum of all activity variances is 64, while the sum of variances along the critical path is 36.
 
  What is the probability that the project can be completed between days 108 and 120?
  A) -2.00
  B) 0.0227
  C) 0.1058
  D) 0.4773
  E) 0.9773
Read 37 times
1 Reply
Introduction to Operations and Supply Chain Management, 4e (Bozarth/Handfield)
Replies
Answer verified by a subject expert
monmon
wrote...
Top Poster
Posts: 914
Rep: 8 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

bsktball509 Author
wrote...

6 years ago
Thank you, thank you, thank you!
wrote...

Yesterday
Just got PERFECT on my quiz
wrote...

2 hours ago
Helped a lot
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  980 People Browsing
Related Images
  
 1037
  
 83
  
 630
Your Opinion
What percentage of nature vs. nurture dictates human intelligence?
Votes: 432

Previous poll results: What's your favorite coffee beverage?