A PERT/CPM activity has an optimistic time estimate of 4 days, a most likely time estimate of 6 days, and a pessimistic time estimate of 10 days. The standard deviation of this activity is:
 
  A) 7/6.
  B) 1/3.
  C) 2/3.
  D) 1.0.
Read 45 times
1 Reply
Replies
Answer verified by a subject expert
schoolboy4367schoolboy4367
wrote...
Top Poster
Posts: 1181
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

zhamila Author
wrote...

6 years ago
Thanks
wrote...

Yesterday
This calls for a celebration Person Raising Both Hands in Celebration
wrote...

2 hours ago
Brilliant
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  846 People Browsing
 107 Signed Up Today
Related Images
  
 263
  
 2502
  
 348
Your Opinion
Which industry do you think artificial intelligence (AI) will impact the most?
Votes: 379