Which is NOT true of the critical path?
 a. The activities on the critical path take the shortest time to complete.
  b. The activities on the critical path define the total project completion time.
  c. It is the project path with zero slack.
  d. The delays in critical path activities will delay the project.
Read 48 times
1 Reply
Replies
Answer verified by a subject expert
apugs211apugs211
wrote...
Top Poster
Posts: 964
Rep: 5 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

batuayan Author
wrote...

6 years ago
I appreciate what you did here, answered it right Smiling Face with Open Mouth
wrote...

Yesterday
Thank you, thank you, thank you!
wrote...

2 hours ago
Helped a lot
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1694 People Browsing
Related Images
  
 801
  
 1459
  
 640
Your Opinion
What's your favorite coffee beverage?
Votes: 303