The Baker county government has decided to redo the street and plans to block the street off which causes considerable inconvenience to people. The critical path method (CPM) project has three sequential (in series, that is i is first, then ii and finally iii..) paths defined as follows: (i) path A-B-C-H to install street lights and electrical wiring that takes 10 days, (ii) path G-J-K-L to install sidewalks with handicap capabilities that takes 20 days, and (iii) path U-V-Z-W to repave the street including storm drains that takes 8 days. Which one of the following statements is true?
 a. The expected duration of the project is 10 + 20 + 8 = 38 days.
  b. The expected duration of the project is 20 days.
  c. The normal time is inversely related to the crash time.
  d. The three sub-system precedent relationships are in parallel.
Read 62 times
1 Reply
Replies
Answer verified by a subject expert
shelbydickersonshelbydickerson
wrote...
Top Poster
Posts: 860
Rep: 6 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

wrote...

6 years ago
Thanks
wrote...

Yesterday
This helped my grade so much Perfect
wrote...

2 hours ago
this is exactly what I needed
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1000 People Browsing
Related Images
  
 85
  
 345
  
 577
Your Opinion
What's your favorite funny biology word?
Votes: 334