zhamila zhamila
wrote...
Posts: 705
Rep: 0 0
6 years ago
In a PERT analysis, the most likely time is the minimum possible time required to complete an activity.
  Indicate whether the statement is true or false
Read 52 times
1 Reply
Replies
Answer verified by a subject expert
dgonzalez228dgonzalez228
wrote...
Top Poster
Posts: 1198
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

zhamila Author
wrote...

6 years ago
Helped a lot
wrote...

Yesterday
Thanks
wrote...

2 hours ago
Thanks
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1578 People Browsing
Related Images
  
 68
  
 76
  
 639
Your Opinion
What's your favorite coffee beverage?
Votes: 303

Previous poll results: Do you believe in global warming?