In the context of the Critical Path Method (CPM), the slack time (ST) for an activity is computed as:
 A) the latest start (LS) time minus the earliest finish (EF) time.
  B) the latest finish (LF) time minus the earliest start (ES) time.
  C) the latest start (LS) time minus the earliest start (ES) time.
  D) the earliest finish (EF) time minus the latest start (LS) time.
Read 79 times
1 Reply
- - UCLA Student
Replies
Answer verified by a subject expert
taniaaaaaataniaaaaaa
wrote...
Top Poster
Posts: 946
Rep: 5 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

Tu Truong Author
wrote...

6 years ago
This calls for a celebration Person Raising Both Hands in Celebration
wrote...

Yesterday
Brilliant
wrote...

2 hours ago
this is exactly what I needed
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1283 People Browsing
Related Images
  
 1378
  
 849
  
 348
Your Opinion
What's your favorite coffee beverage?
Votes: 274