Which of the following is true of earned value?
 a. It is the actual cost plus the planned cost.
  b. It is based solely on the total cost estimate to be spent on an activity.
  c. It is an estimate of the value of the physical work actually completed.
  d. It is also known as the planned value.
Read 51 times
1 Reply

Related Topics

Replies
wrote...
6 years ago
c