A backward pass through the network diagram determines the early start and early finish dates for each activity.
 a. True
  b. False
  Indicate whether the statement is true or false
Read 71 times
2 Replies
Replies
Answer verified by a subject expert
bhodgesbhodges
wrote...
Top Poster
Posts: 1244
Rep: 8 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

johnwayne88 Author
wrote...
6 years ago
What an excellent community, thanks for answering
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  958 People Browsing
Related Images
  
 248
  
 314
  
 2037
Your Opinion
Which of the following is the best resource to supplement your studies:
Votes: 292

Previous poll results: Who's your favorite biologist?