In a PERT network, a/an _____ is the latest time an activity can finish without delaying the entire project.
 a. late start
 b. late finish
 c. on time finish
  d. early start
 e. late start
Read 28 times
1 Reply
Replies
Answer verified by a subject expert
leannaolsenleannaolsen
wrote...
Top Poster
Posts: 875
Rep: 3 0
6 years ago
Sign in or Sign up in seconds to unlock everything for free
1

Related Topics

wrote...

6 years ago
Helped a lot
wrote...

Yesterday
This calls for a celebration Person Raising Both Hands in Celebration
wrote...

2 hours ago
Brilliant
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1020 People Browsing
Related Images
  
 202
  
 4813
  
 377
Your Opinion