After investing resources in thoroughly understanding the business problem, the analyst decides that the costs of solving the problem will likely outweigh the benefits. The analyst should ____.
 a. move to the design activities
 b. invest more in the project to increase the benefits
  c. resolve feasibility issues
 d. suggest that the project be discontinued
Read 77 times
1 Reply

Related Topics

Replies
wrote...
7 years ago
d