What is the production plan for all finished goods?
 a. MPS - master production schedule c. PPR - production planning run
  b. QQR - quality query run d. RUN - run
Read 64 times
1 Reply

Related Topics

Replies
wrote...
6 years ago
A
The output of the demand management process is the master production schedule (MPS), which is the production plan for all finished goods.