× Didn't find what you were looking for? Ask a question
Top Posters
Since Sunday
5
a
5
k
5
c
5
B
5
l
5
C
4
s
4
a
4
t
4
i
4
r
4
New Topic  
ExistentlAngst ExistentlAngst
wrote...
Posts: 633
Rep: 1 0
6 years ago
What is the production plan for all finished goods?
 a. MPS - master production schedule c. PPR - production planning run
  b. QQR - quality query run d. RUN - run
Read 71 times
1 Reply

Related Topics

Replies
wrote...
6 years ago
A
The output of the demand management process is the master production schedule (MPS), which is the production plan for all finished goods.
New Topic      
Explore
Post your homework questions and get free online help from our incredible volunteers
  1295 People Browsing
Related Images
  
 327
  
 343
  
 347
Your Opinion
What's your favorite math subject?
Votes: 293